How to Change the Working Days in the Gantt Chart

To change the working days for the current project:

  1. Open the "File" menu
  2. Hover the mouse over "Prepare" then select "Map Properties"
  3. Switch to the "Calendar" tab
  4. Check the days that you want to be working day
  5. Click "OK"

Once the working days have been changed the Gantt chart will automatically update.

To change the working days for all future projects:

  1. Switch to the "Tools" ribbon
  2. Click "Options"
  3. Switch to the "Project Options" tab
  4. Check the days that you want to be working days
  5. Click "OK"

New projects created from now on will inherit these settings.


Change Working Days for the Current Project
Is_it_possible_to_add_holidays_or_days_off_to_my_project_4.png
How_do_I_change_the_working_days_in_the_Gantt_5.png
Change Working Days for all Future Projects
How_do_I_change_the_working_days_in_the_Gantt_6.png
How_do_I_change_the_working_days_in_the_Gantt_7.png